PAGES/LINE
|
TOPIC
|
SUMMARY
|
3:1-7
|
Location
|
Ace, Smith & Jones LLP, 700 Westfield Road,
Suite 220, Fresno, CA
|
3:12-25
|
Appearances
|
Mike Counsel, Ace, Smith & Jones LLP –
Attorney for plaintiff
Christine Lewis, Law Offices of Christine M. Lewis
– Attorney for defendant
|
4:4-6
|
Name
|
Examination
by Mr. Counsel
Witness’ name is John Supervisor.
|
4:7-22
|
Prior
depositions
|
Witness has had his deposition taken on one
previous occasion; he DNR how long ago it was. It was in connection with a
work matter, and he was working at BuildCorp at the time. It was within the
last 10 years. He DNR if it was in connection to a job site accident.
|
4:23-9:8
|
Admonitions
|
Admonitions were reviewed.
|
9:9-20
|
Witness’
residence address
|
Witness’ residence address is 158 Slimline Street,
Redwood City, CA, 94063. He has lived there for more than 10 years. He might
move in the next few years but not immediately.
|
9:21-10:3
|
Witness’
phone numbers
|
His telephone number is (650) 555-5555. His cell
phone number is (650) 444-4444.
|
10:4-25
|
Current
employment
|
Witness is currently working for BuildCorp
Builders as a labor foreman. He has worked for them for more than five years.
He DNR if he was working for them in the 1980s. He has been a labor foreman
for BuildCorp since he joined them.
|
11:1-18
|
Previous
employment
|
Prior to BuildCorp, witness worked for Belcore
Construction in Campbell or Los Gatos, for four to five years. He was a
laborer for them. He has not been a labor foreman for any company other than BuildCorp.
He has never worked for BuildCorp as a laborer rather than a foreman.
|
11:18-19
|
Date
of birth
|
Witness’ date of birth is 2/25/1956.
|
11:20-21
|
Remaining
time at work
|
Witness plans to continue working for two to three
more years.
|
11:22-24
|
Who
witness reports to
|
Witness reports to Thomas Pointer.
|
11:25-12:17
|
Four
Market Street project
|
Witness recalls the Four Market Street project. He
was reporting to Mr. Pointer on that project. He was the laborer foreman on
that project. He DNR how long he worked on that project but it was not more
than one year. It may have been last year but he DNR.
|
12:18-13:7
|
Laborers
working for witness on project
|
The number of journeyman laborers working for
witness on the project varied during different points of the project. He
generally had around eight laborers. He supervised them and was a working
foreman.
|
13:8-14:1
|
Witness’
function on project
|
Witness’ function was focused on doweling and
epoxying rebar. It was a seismic retrofit project which included reinforcing
the concrete with rebar. This was necessary in the perimeter walls, which
were made of brick and concrete.
|
14:2-15
|
Laborers’
work
|
The laborers that witness supervised did the same
work. While he was there, they did not have any other responsibilities
besides doweling and epoxying rebar. Witness was in charge of all the
laborers.
|
14:16-25
|
Laborers
cleaned up on previous projects
|
On other projects, there have been occasions where
witness has supervised laborers that have cleaned up after other
subcontractors for which BuildCorp would then charge that subcontractor for
the cleanup. Witness DNR any of this happening while he was on the Four
Market project.
|
15:1-3
|
Equipment
used to drill holes for dowels
|
Witness used rotary hammers to drill the holes for
the dowels.
|
15:4-24
|
What
laborers did on a typical day
|
On a typical day, witness would direct the
laborers to get the right size bars that they were installing, make sure that
they had all the epoxy they needed, inspect the holes that they were blown
correctly before they put the epoxy, and check the layout for the next
day. A carpenter foreman would check
the layout ahead of them and witness would go to him to make sure that they
were done to what they needed. A layout guy would mark the locations for the
drilling. It was a carpenter.
|
15:25-16:9
|
Subcontractors
involved on project
|
When witness arrived on the project, the other
subcontractors involved were Boston Wrecking doing the demolition, SteelCo
Steel bringing in all the steel beams and so on, and electricians, whose
company witness DNR.
|
16:10-15
|
No
rain on project
|
Witness DNR what season it was when he started on
the project. There was no rain.
|
16:16-17:3
|
BuildCorp
safety meetings
|
Witness attended safety meetings on the project.
He DNK when the meetings were held. Most likely it was Ferguson, the
carpenter foreman, who ran the meetings. Witness DNK his last name. The
meetings were just for BuildCorp employees.
|
17:4-9
|
Coordination
meetings with subcontractors
|
Witness is not aware of coordination meetings that
took place between BuildCorp and the subcontractors. He DNR attending these.
|
17:10-18:9
|
What
transpired at safety meetings
|
The topics covered in the safety meetings that
witness attended were different every time. There were no pictures but there
were letters on a pre-printed form. Whoever conducted the meetings read the
form to attendees. Discussion followed about the safety topic. If anybody had
an issue they wanted to raise about that topic, they could bring it up. There
was also the opportunity for people to bring up safety concerns that they had
that were not related to that topic. If somebody encountered a safety issue
in the week prior, that was a forum for people to discuss the safety issue.
|
18:10-19:3
|
No
discussion or concern about trades working close to one another
|
Witness never heard anything during any of the
safety meetings that he attended about concerns about the different trades
working in close proximity to one another. Witness never heard anybody raise
any concern about debris falling from the demolition down on people. Witness
did not have any understanding that there were instances where Boston
Wrecking had caused debris to fall down on other trades. Witness did not have
a sense that the trades were working too closely to one another.
|
19:4-18
|
Direction
to work locations
|
Witness was guided by a carpenter to the location
where he would be working the following day. Witness DNK if BuildCorp
personnel were directing the various subcontractors to where they would be
working on any given day.
|
19:19-20:1
|
Did
not have to stop work because of another trade in the area
|
There were never any occasions in which witness
had to stop his work because another trade was going to be coming into the
area where he was working. There were no occasions where witness couldn’t do
his work because another trade was working in the area.
|
20:2-12
|
Special
inspector addressing quality of work
|
Besides witness, a special inspector which was a
different contractor than BuildCorp, inspected the work they were doing.
Witness DNR who that individual worked for. The person was inspecting the
quality of the work being done.
|
20:13-21:4
|
Safety
inspections
|
Witness DNK who was in charge of safety because
his job was to do the doweling and epoxy. It was normal procedure for
BuildCorp to do safety inspections. Witness DNK who did the inspections or if
it was more than one person.
|
21:5-22:14
|
Instances
in which witness has seen unsafe work by subcontractors in his career
|
While working for BuildCorp, witness DNR seeing a
subcontractor on a project working unsafely. If witness assumes he is on
project where BuildCorp is the general contractor and he sees a subcontractor
performing work unsafely, witness stops him. Witness DNR if, in his career,
he has stopped a subcontractor who he felt was doing something unsafe; it
might have happened. There have been occasions where witness has seen a
subcontractor working without a hard hat and he said “Put on your hard
hat”. Witness has not seen a
subcontractor to BuildCorp working without eye protection and told them to
put their eye protection on. There have been occasions where witness has seen
a subcontractor to BuildCorp working without hearing protection and he has
said “wear hearing protection.” Witness has not seen a subcontractor not
wearing fall protection and said “You’ve got to have fall protection”.
When witness has said “Put on your hard hat” or
“Put on your hearing protection,” it’s just taken care of at that point.
|
22:15-23:5
|
No
recollection of unsafe work on Four Market project
|
If witness saw a subcontractor performing unsafe
work on the Four Market project, he could have the subcontractor stop and
correct the unsafe practice. Witness DNR any such instances. Witness DNK if
there was at least an occasion where that did occur.
|
23:6-12
|
Slab
grabbers
|
Witness recalls on the Four Market project that
there were locations where there were guardrail systems that used slab grabbers.
The locations were where the demolition was ahead of them.
|
23:13-21
|
Regular
work sequence
|
The regular work sequence was Boston going through
a particular area first performing their demolition, followed by BuildCorp,
followed by SteelCo Steel.
|
23:22-24:20
|
Installation
of slab glabber railing systems by BuildCorp
|
There were occasions where witness followed the
work of Boston Wrecking where they might have created a floor opening and
there would be a slab grabber railing system. BuildCorp installed those
railing systems. Witness did not have any involvement in the installation of
those railing systems. To his knowledge, none of his laborers were involved
in the installation of those railing systems. That would typically be handled
by the BuildCorp carpenters.
|
24:21-26:14
|
How
slab grabber railing systems are installed
|
Witness has watched the installation process for
the slab grabber railing systems. The metal post has a leg on the bottom that
gets adjusted from the post, top of post. It has a nut that you turn with a
crescent wrench, slide it in the slab, the end of the slab, and you tighten
it up. After that you install two-by-fours, two of them, at different
elevations. The two-by-fours are not affixed to the slab grabbers with
screws. They are not wired to the slab grabber. It has a nail so it doesn’t
slide to the sides. BuildCorp carpenters insert those nails; it is always
done. It’s a safety policy that the two-by-fours be nailed so that they don’t
slide in the slab grabber. Witness has seen them installed when he walked
through the areas where they’re doing it.
|
26:15-27:5
|
Witness’
replacement of slab grabber
|
Witness has had to replace a slab grabber. He does
not carry a crescent wrench with him. When he has had to replace a slab grabber,
he has to go get a crescent wrench to do so or call somebody near him to lend
him a tool. Witness learned how to replace a slab grabber in his career.
Witness did not replace any of the slab grabbers on the Four Market project.
|
27:6-28:3
|
What
witness typically carries
|
Witness typically carries his radio. He keeps his
wrench handy. If he didn’t have it at the time, he would get somebody near
him with a crescent wrench. He would then have to re-nail the two-by-fours
into the slab grabber. Witness has a hammer among his tools. There are
usually boxes of nails nearby the areas they are working on.
|
28:4-25
|
Tightening
of slab grabber
|
Witness most likely uses a number 10 wrench to
tighten a slab grabber down. He tightens the slab grabber as tight as
possible. He turns it until it can’t be turned anymore. To make sure it is
affixed to the slab well, he grabs it and shakes it a little. If it needs
more tightening, then he tightens it. It should butt right to the edge of the
concrete; there is no play acceptable. It shouldn’t move at all.
|
29:1-7
|
Analysis
when re-attaching slab grabber
|
When re-attaching a slab grabber, witness analyzes
that there is a flat surface underneath and a flat surface on top so that it
sets right.
|
29:8-30:20
|
Force
applied to slab grabber
|
Witness DNK how much force a slab grabber is
supposed to be able to withstand if installed properly. He DNK if there is
any difference in the amount of force a slab grabber is supposed to be able
to withstand at the top versus at the base. Witness has never seen a slab
grabber get knocked off. He has seen people, but nothing else, leaning on
slab grabbers. He considers it safe to lean against a safety railing. Witness
has never seen a slab grabber with sort of handles on top.
|
30:21-31:1
|
Replacing
slab grabber
|
When witness has replaced a slab grabber, it is
something he was asked to do by his superintendent.
|
31:2-19
|
Taking
down slab grabbers
|
Witness has seen slab grabber railing systems that
were down to allow some work to take place. He has been asked by his
superintendent to take down a slab grabber system. He was not asked to do so
on the Four Market project. It is generally in the realm of the carpenters to
handle the slab grabbers but witness might step in if the carpenters were not
available.
|
31:20-32:10
|
Safety
concern when slab grabber is down
|
When a slab grabber is down it is always a safety
concern. If it is down, he puts it right back up. He never left the area
unattended. If there is work taking place in the area, he would most likely
advise everybody and tell them “There is work going on, stay away from the
area,” and then keep an eye on it to make sure that, once the job is done in
that area, they are put back the way they were.
|
32:11-33:15
|
Removal
of slab grabbers around a stairwell opening
|
If the slab grabber is in the way of people
installing a stairway, for example, then witness or a carpenter would be
directed by his supervisor to remove it while they are doing their work.
Witness DNK if in the process of installing new stairs in an existing
structure, like the Four Market project, the slab grabbers around a stairwell
opening will from time to time need to be lowered to allow the stairwell work
to take place. Witness did not see slab grabbers down around stairwell
openings on the Four Market project. He has seen them down around stairwell
openings on other projects while there are other people installing that are
doing the job.
|
33:16-34:3
|
What
witness would do if subcontractor removed slab grabber
|
Witness has never in his career seen
subcontractors to BuildCorp either removing or replacing slab grabbers. If he
saw a subcontractor removing a slab grabber to perform work in a stairwell
opening, he would inform his supervisor because it is their responsibility to
do that. They should go straight to them to have them removed.
|
34:4-22
|
What
witness would do if subcontractor removed two-by-fours
|
If witness saw a subcontractor removing the
two-by-fours and not the slab grabbers in order to perform their work, he
would put them right back up. If it’s a quick move, he would do so right
away. If it’s going to take a long time, he would go to his supervisor and
discuss it. If it were going to be a long time, he would try to take care of
it right away so that it wouldn’t be a safety issue.
|
34:23-35:24
|
Has
seen stringers and railings lowered into stairwell openings
|
Witness has seen stringers lowered into a
stairwell opening. The stringers are separate pieces from the railings.
Witness has seen railings lowered into the stairwell openings. It is
typically done by putting a cross member, which is an I-beam, up high, and
then some come-alongs with chains to hoist them or lower inside the shaft
where they’re installing the stairways. When witness has seen stringers and
railings lowered, he has not seen the two-by-fours removed in order to allow
the access of those items, because they usually do it inside the shaft. They
hoist them up and down. They lower from the top or bottom.
|
35:25-37:17
|
Lowering
of stringers and railings from a lower floor
|
Witness has seen stringers and railings lowered
from a particular floor down on a retrofit project of an existing structure.
Slab grabbers were present on those occasions. It has been necessary to
remove the two-by-fours only in a slab grabber railing system when the actual
lowering takes place. It is not a five-minute project but witness DNK how
long it would take because he doesn’t work in that field.
|
37:18-38:12
|
Talk
with supervisor if two-by-fours were to be down
|
When witness has seen two-by-fours down in the
midst of the process of lowering stringers into stairwell openings, from a
safety perspective he has talked to his supervisor, who would inform him
what’s going on in the area so witness knows what they are doing. He would
expect to know beforehand that the railings were going to be removed.
|
38:13-23
|
Morning
meetings with Lenahan or Pointer
|
In a typical week on the Four Market project,
witness would not know what the other trades were going to be doing. He met
in the morning with Mr. Lenny or Mr. Pointer. He was concerned about his
area, his job, his progress. He was not involved in the other part of the
work.
|
38:24-41:1
|
Advance
notice of stringers being lowered on other projects
|
When witness has seen stringers lowered into
stairwell openings on other projects, he was told in advance by his
supervisor over the radio that this would occur. In his career, witness has
not seen two-by-fours in slab grabber railing systems removed without being apprised
by his superintendent that it was going to occur.
|
41:2-19
|
No
awareness of stringers lowered at Four Market
|
Witness was not aware of the stringers being
lowered in on the Four Market project because he wasn’t working near the
stringers. He was probably not on the job site at the time; he was in the
project.
|
41:20-42:8
|
Slab
grabbers with plywood barrier
|
Witness has never seen slab grabber railing
systems which have also been accompanied by a plywood barrier. BuildCorp
wouldn’t set up plywood with the slab grabber railing system.
|
42:9-43:12
|
Barricades
around floor openings
|
On the Four Market project, there were cuts in the
floor openings. Witness saw demolition occurring on the project. If
demolition was taking place near a floor opening, they barricaded the area on
the columns to keep people from going to where the demolition was taking
place.
|
43:13-45:7
|
Demolition
witnessed
|
Witness saw demolition of part of the floor
opening facing Market St. and part of the floors, meaning the floor
structure, going to their neighbors, which is a hotel. There were four to
five floors on the project, and demolition occurred on most of them. Some of
the demolition involved creating floor openings. Some was near the columns.
The railing that supports the cart and the cart of the old freight elevator
were demolished. The elevator hoistway was still in place. Jackhammers and
Bobcats were used for the demolition. Witness DNR any other equipment used.
|
45:8-24
|
Purpose
of holes in floors
|
The holes created in the floors were to put in
electric escalators, and to add some concrete beams for the retrofit. Witness
DNK that the holes were being created for stairwells.
|
45:25-47:21
|
Red
caution tape comprised barricades
|
Where the demolition occurred, the floors were
barricaded. Witness DNK who erected the barricades. Boston Wrecking did the
demolition. The barricades around the demolition work that witness saw
consisted of red caution tape that goes from column to column. This indicates
a line that you are not supposed to cross. Yellow tape indicates a line that
can be crossed with caution. Most likely Boston erected the red caution tape.
Witness never saw any barricades besides the red caution tape.
|
47:22-48:16
|
Prevention
of debris exiting main area of project
|
Witness has seen systems designed to contain
debris on the project; they were intended to prevent debris from exiting the
project site. He saw a netting and a shoot. They were designed to prevent the
debris from getting outside the main area of the project.
|
48:17-49:17
|
Covering
holes with plywood
|
Witness never saw any holes created in the
exterior of the building. He saw holes on the project that were covered with
plywood that was nailed down. To affix the plywood to a concrete floor, you
attach it with a 16 nail duplex that has a double head and a piece of wire.
Before that, you drill the hole through the plywood to the concrete with a
bull dog that has a 3/16 inch bit. Then you pound the nail and the wire to
plywood to concrete. Witness did not do that kind of work; it is the
carpenter’s work. The plywood used to cover the holes was commonly 5/8 or ¾.
|
49:18-50:9
|
Warning
on open hole
|
When plywood is placed over a hole, witness does
not consider that to be a tripping hazard. It’s only ¾ or 5/8 thick. Once
it’s applied, they put a sign on it saying “Open hole.” Nobody should be
walking or rolling anything on top of it.
|
50:10-19
|
No
barricades around hole
|
Witness did not see any barricades, railing
systems, or anything set back from the hole opening itself.
|
50:20-22
|
No
recall of other railing systems
|
Witness DNR seeing any other railing systems apart
from slab grabber on the Four Market project.
|
50:23-52:16
|
Protection
of flooring on ground floor
|
On the ground floor of the project, inside,
witness moved materials. The floor surface was concrete. On occasions,
witness was advised that small, old, existing penetrations in the flooring
needed to be protected on the ground floor in certain locations. Decorative
flooring also had to be protected, in the center of the main ground floor,
first floor. They used plywood to protect that flooring the entire time he
was there. Steel plates were used on the ground floor to protect the transit
of the Bobcats when they were traveling on the floor. Witness did not see the
floor beneath that needed protecting.
|
52:17-22
|
No
railing systems affixed to steel plates
|
Witness has not seen any railing systems welded to
or affixed in any way to the steel plates.
|
52:23-53:13
|
Use
of plywood in construction areas
|
Witness had never seen BuildCorp use plywood in
conjunction with a slab grabber railing system. They have built some walls
with plywood behind the construction areas, like barricades, but not to
contain any load. Witness has never seen plywood erected around a stairwell
opening to prevent debris from going in the stairwell.
|
53:14-54:20
|
Recall
of outhouses in photograph
|
The photographs Bates stamped Boston 712-731 were
taken in 2004. Witness recognizes the outhouses and portables in Boston 713.
He DNK how long they were there. Witness DNR what is depicted in 714. He only
remembers where the outhouses were. He DNR how this looked.
|
54:21-24
|
Exhibit
1
|
Exhibit 1
Photograph Bates stamped Boston 714 was marked for
identification.
|
54:25-55:18
|
Exhibit
1
|
In Exhibit 1, the exit was on this side, behind
this wall. The entrance and exit to the project was a door with a chain,
little ramp, and then outhouses. The outhouses were kept inside in the same
place during the day. Apart from the two outhouses, witness does not
recognize much in Exhibit 1.
|
55:19-20
|
Exhibit
2
|
Exhibit 2
Photograph was marked for identification.
|
55:21-56:11
|
Debris
in Exhibit 2
|
Exhibit 2 is a slightly different perspective of
the general area of photo 1. There is a little more debris over here than
over here (indicating). Witness did not often see piles of debris on the
ground level. If there was, it was something like the size of the pile in
photograph 2.
|
56:12-58:8
|
Removal
of debris from ground floor
|
Witness saw Boston Wrecking personnel using a
Bobcat on the ground floor to remove debris from the premises where the main
demolition was, and it was usually done with a wheelbarrow and some of their
laborers.
There were not many occasions when witness saw
piles of debris on the ground floor similar to the one in Exhibit 2. They
were pretty good at keeping everything in their demolition areas. He saw
debris piles similar to the one in Exhibit 2 on the ground floor of the
project while the demolition was in progress. He saw Boston Wrecking
personnel using wheelbarrows to remove debris piles by that were of the size
seen in Exhibit 2. They used manual labor, shovels, to load the debris into
the wheelbarrows. They also used Bobcats. Whether they used Bobcats versus
wheelbarrows and shovels depended on the size of the debris pile.
|
58:9-59:12
|
Removal
of debris from upper floors via shoot
|
Witness DNK where the debris was taken, besides
that it was taken outside. Debris was removed from the upper floors and taken
to the lower floors via an internal shoot which landed right on the ground
floor. Witness DNR if there was a barricade off the area where debris fell
onto the ground floor. He DNR whether there was anything to contain the
debris as it fell through the shoot to the ground floor.
|
59:13-61:22
|
What
witness would do if he saw a debris pile pushed against plywood and slab
grabbers
|
There were two floors below the ground level.
Witness DNR the stairwell opening on the other side of the plywood in photograph
2. If witness had seen Boston Wrecking personnel using a Bobcat to load a
debris pile the size seen in Exhibit 2, during which he saw them pushing the
debris pile so that it was pressing up against the plywood and the slab
grabbers, he would have stopped them because if they would push this, the
force of the slab grabbers is not to support the force of a piece of
equipment of hat size. He would be concerned that the plywood and slab
grabber could get knocked into the stairwell. He would expect a competent
Bobcat operator to not push debris up against plywood and a slab grabber that
surrounded a stairwell opening.
|
61:23-62:3
|
No
knowledge of schedule for debris removal
|
Witness was not aware of any schedule with regard
to removal of debris on the project, or any limitations as to when debris
could or could not be removed.
|
62:4-16
|
Work
hours
|
Witness started work on the project at 6:30 and
left at 3:30. He DNR if there were crews that continued to work after he
left. He DNR if there was overtime demolition.
|
62:17-24
|
Did
not hear about accident on project
|
Witness recently heard about the incident involved
in the current action. He didn’t hear about it while working on the project.
|
62:25-63:10
|
Debris
removal while ironworkers in stairwell
|
Witness DNK of any reason why debris removal would
have to have taken place at the same time that ironworkers were working in
the stairwell in photograph 2.
|
63:11-64:16
|
Who
witness knew on project
|
Witness knew two ironworkers on the project, Mario
and the foreman, whose name he DNR. Witness has never heard of John Smith.
The foreman was Latin. Witness is not sure if he knows the name Jessie Jones.
Witness did not know these people prior to the Four Market project. The
discussions he had with them were nothing beyond “Hello, how are you, how are
you doing”. He never had lunch with any of them. Witness knew the Boston
Wrecking personnel when he met him on the job, but not before that. He didn’t
have any discussions with these personnel beyond “Hello, how are you?”
|
64:17-20
|
When
witness learned of incident
|
Witness’ first knowledge about the incident in
question was when he learned of his deposition.
|
64:22-66:1
|
Witness’
demolition work history
|
Examination
by Ms. Lewis
Witness has done demolition work while working for
BuildCorp. He has done it off and on; the longest period was around three
months on one project. He has been doing demolition work off and on since he
started as a laborer. He did not do any demolition work on the Four Market
project.
|
66:2-18
|
No
unsafe work by Boston
|
Witness DNR any instances where he saw Boston
working unsafely. He recalls them operating the Bobcat. He DNR them operating
the Bobcat unsafely. It is common to use Bobcats on retrofit projects.
|
66:19-67:5
|
Debris
shoot used by Boston Wrecking
|
Boston Wrecking set up the debris shoot. It was an
existing tube, a big tube that was there. He DNK the reason it was there.
Boston Wrecking was using it for their debris.
|
67:6-11
|
Slab
grabbers and plywood
|
Witness did not see Boston removing any slab
grabbers on the project. He DNR if Boston had its own plywood on the project.
|
67:12-68:1
|
Boston
employees that witness knew
|
Witness has worked with Boston Wrecking on three
to four projects. He knew some of the Boston employees. The only name he can
remember is Popo; he DNK if that is his first or last name. He didn’t know
the others by name, just “Hello, how are you.” He DNR any of the Boston
employees that were working on Four Market.
|
68:3:69:16
|
Safety
during demolition work for BuildCorp
|
Further
Examination by Mr. Counsel
When witness has done demolition for BuildCorp, he
has endeavored to do so in a safe manner. He gets a sense of his surroundings
and who’s working around him. Most of his demolition work has been carried
out by BuildCorp with nobody else around. Their normal safety procedure is to
not drop something on somebody below when they are doing demo. This applies
to any work they perform.
|
69:17-69:23
|
Use
of backhoe and Bobcat
|
Witness has never used a backhoe for BuildCorp. He
has used a Bobcat for BuildCorp. A backhoe is typically operated by an
operating engineer.
|
69:24-71:8
|
When
to use Bobcat vs. wheelbarrow and shovel
|
Witness is aware of projects where Bobcats are
used because the environment is not large enough for a backhoe. He is aware
of environments he has worked in previously that do not permit a Bobcat, and
they have to use wheelbarrows or shovels. In deciding whether to use a Bobcat
rather than a wheelbarrow or shovel, one item for consideration is whether it
can be done safely with a Bobcat.
|